Industry Odisha Bureau, Sep 03: A senior HD Hyundai delegation visited Thoothukudi this week for shipyard talks. The discussions form part of India’s broader greenfield shipbuilding cluster programme. Officials met representatives from V.O. Chidambaranar Port and Tamil Nadu’s government. Thoothukudi ranks among five proposed shipbuilding clusters nationally. The project has moved beyond its initial conceptual planning stage.
HD Hyundai, among the world’s largest shipbuilders, sent delegates for talks. Discussions centred on establishing a major shipbuilding facility locally. The Centre proposes five greenfield clusters across India’s coastline strategically. Full central capital assistance is proposed for shared infrastructure development. Thoothukudi has reportedly emerged as the most advanced cluster.
The proposed Thoothukudi cluster spans roughly 2,050 acres of land. It includes a waterfront stretching approximately 2.4 kilometres in length. The site offers a draft depth of about five metres. This location sits adjacent to V.O. Chidambaranar Port’s existing infrastructure. Thoothukudi is reportedly the only cluster with an identified investor.
Project preparation has advanced through several formal procedural stages already. A special purpose vehicle has been formed for execution. A techno-economic feasibility report has also been completed formally. In-principle approval has been granted for the proposed project. These milestones, however, do not indicate construction has begun.
Around 1,500 acres of the identified land remain available currently. This includes government-owned land and land under private access arrangements. Roughly 300 acres consist of salt pans requiring separate acquisition. Acquiring this salt-pan land remains a genuine implementation challenge. Some landowners have reportedly raised objections regarding the acquisition process. Discussions are reportedly underway to help resolve these disputes.
HD Hyundai announced in December 2025 it had selected Thoothukudi. The announcement identified the coastal town for a proposed shipyard. The company has not officially disclosed its investment figure yet. Sources had indicated the investment could total around $2 billion. This estimate remains source-indicated rather than an official company disclosure.
India’s shipbuilding ambitions extend beyond the Thoothukudi project alone. Four other clusters are proposed across different coastal states. These include locations in Andhra Pradesh, Gujarat, Maharashtra and Odisha. Each cluster aims to build integrated shipbuilding ecosystems around waterfront access. Building such capacity typically requires supply chains, skilled labour and sustained execution.
The Thoothukudi project illustrates the gap between announcement and operation. Selecting a location differs meaningfully from securing full land acquisition. Preparatory approvals differ from actual construction and financial closure. The coming months will likely determine whether land disputes resolve. HD Hyundai’s continued engagement suggests sustained interest in the site. Still, execution challenges remain before Thoothukudi becomes an operating shipyard. The project’s progress could shape India’s wider shipbuilding cluster strategy.